EMERGENCY TIMELINE (from court transcripts):
1. Initial Procurement (3 weeks/21 days)
- VA needs this time to process contracts
- Cannot be shortened due to government contracting requirements
- Described as "very aggressive" timeline by VA
2. Manufacturing Timeline (from Cavco)
- 2 weeks after purchase order to begin production
- Production rate: 15 units per week
- Total manufacturing time: 8.5 weeks for first 50 units
- Delivery from Arizona via truck
3. Total Timeline:
- Procurement: 21 days
- Start-up: 14 days
- Manufacturing: ~60 days
- Total: Approximately 90 days
UNIT SPECIFICATIONS (mentioned in documents):
- Must be dignified and respectful units
- Must meet disabled access requirements
- Units would be uniform for improved operations
- Require DMV registration
- Need to be relocatable